Art. 73 CISG
(1) In the case of a contract for delivery of goods by instalments, if the failure of one party to perform any of his obligations in respect of any instalment constitutes a fundamental breach of contract with respect to that instalment, the other party may declare the contract avoided with respect to that instalment.
(2) If one party's failure to perform any of his obligations in respect of any instalment gives the other party good grounds to conclude that a fundamental breach of contract will occur with respect to future instalments, he may declare the contract avoided for the future, provided that he does so within a reasonable time.
(3) A buyer who declares the contract avoided in respect of any delivery may, at the same time, declare it avoided in respect of deliveries already made or of future deliveries if, by reason of their interdependence, those deliveries could not be used for the purpose contemplated by the parties at the time of the conclusion of the contract.
Secretariat Commentary
The Secretariat Commentary on Art. 64 of the 1978 New York Draft, predecessor to Art. 73 CISG, gives insight into the drafters' unterstanding on the eve of the 1980 Vienna Diplomatic Conference.
Overview of case law on Art. 73 CISG: UNCITRAL Digest
The UNCITRAL Digest on the CISG can be used as a starting point to discover the relevant case law on this article.